- Lots should be numbered consecutively. Why not adjust lot numbers across both phases instead of using 1000, 1001, 1002?
- Current tree removal permit identifies 1,324 trees being removed. The revised table provided only list 962. Please explain the discrepancy.
RIVERLIGHTS AGE QUALIFIED PHASE 2 AND 3 [TRC Plan Review# 5]
TECHNICAL STANDARDS – ACCESS (driveway, sidewalk, and sight distance):
1. Please ensure the crosswalks adjacent to the newly created 43’ lots, (such as #287, #288 and #318) do not interfere with the residential driveways and tapers for these lots. Please revise on the plans issued for Construction. [SD 3-03.1]
2. The Sidewalk on Floating Bridge Trail and Wilderness Road appears to end at the Multi-Use Trail, instead of extending to River Road. Please show the connection for the final ~85’ between the end of sidewalk and River Road intersection/ bike lanes. Please revise on the plans issued for Construction.
3. No Further Comments
|